Geothermal energy developer Fervo says its contracted revenue rose to $11.9 billion in the third quarter, up from $7.2 billion in the previous quarter. The company's growing project pipeline comes as demand for electricity expands, including from data centers.
At Cape Station in Utah, Fervo has already connected a 100-megawatt geothermal plant to the grid. The company is also advancing a 396-megawatt project for Google, which is scheduled for completion by the end of 2028. Fervo estimates the wider Cape Station resource could ultimately support 8.4 gigawatts of generation.
Modular construction supports phased power supply
Fervo builds its projects in units it calls GeoBlocks, linking several geothermal wells to generate electricity. The company says its first completed unit produced 33 megawatts, while newer units have reached 50 megawatts. This phased approach could allow data-center operators to match new power capacity with demand as construction progresses.
The company is also working to lower construction costs. Fervo reported costs of $7,000 per kilowatt for Cape Station's first phase and $5,500 per kilowatt for the Google project. Its longer-term target is $3,000 per kilowatt.
By combining geothermal generation with staged construction, Fervo's projects could broaden access to steady, lower-emission electricity. Continued progress on cost and delivery will help determine how widely this model can support future energy needs.